Construction Updates -April 2024

Update as on 8th April, 2024

Construction Updates – April 2024

Update as on 8th April, 2024

Tower 1 OC received till the 51st floor!

Titlis - Till 51st Floor OC received
100%
Pilatus
46%
Zermatt
16%

% mentioned above is the current demand due as per the construction linked payment schedule

Tower Name Floor Details Detailed Updates
Titlis
Tower raft – 100% completed
Podium raft-100% completed.
Basement – B1 complete, LG complete, UG complete.
Extended Podium of west & south side in Tower A – 100% RCC completed upto Podium 8th Slab.
Center core CC completed till 58th floor.
Tower 1 OC received till the 51st floor
P1 to P8 podium floors completed, typical floor completed from 9th to 64th floor, terrace slab work in progress.
Center core area casting including LMR completed up to top level.
South & west side balance podium civil work up to P8 completed.
Drop off Area – 100% RCC work completed upto B1 to P7 level & P8 level-  90% RCC work completed.
Finishing work
1) Block work & Gypsum- 9th to 39th floor completed excluding flats on hold. 40th to 51st level block work completed 90% & above floor work in progress . 40th to 51st gypsum work 75% completed. 52nd to 63rd floor block work completed & above floor block work in progress & 52nd & above floor gypsum work 40% completed.
2) Fire fighting -Typical level -9th to 39th floor completed excluding flats on hold. Work in progress on Podium levels – 85% completed & 40th to 51st work 85% completed. 52nd & above floor work in progress.
3) Flat Toilet waterproofing work – 9th to 51st floor all flats work completed & 52nd  above floor work in progress 60% completed.
4) External Painting Single coat completed up to 39th floor & 39B to 51st work in progress.
5) Project lift LW1 & LW2  Installation & Commissioning completed, LW3 is now operational in full speed from UG to 51st floor. LW4 erection work 70% completed.
6) Plumbing Down takes completed up to 39th floor, water supply riser completed up to 39th floor, branch connection work completed for up to 39th floor. Podium level down take work in progress.  kitchen ducts completed up to 51st floor completed & 52nd to 59th work in progress.
7) Typical lobby 9th to 40th floor work completed.41st to 51st floor work 90% completed & 52nd to 59th floor lobby tiling work 80% completed.
8) Mid landing servant toilet completed up to 39th floor , toilet commissioned from 9th to 51st floor work in progress.
9)Copper piping work completed in lobby area.
10) Marble flooring work in progress in sold flat upto 39th floor, 201 flat work completed , 39B to 51st floor marble laying completed 100% & 9th to 39th unsold floor work in progress.
11) Electrical conducting & Choke up clearing work completed up to 63rd floor.
12) Window Installation work 94% completed up to 39th floor, & 40th to 51st floor work 90% completed. 52nd above floor work in progress.
14)Internal Railing work 96% completed up to 39th floor & 40th -51st work in progress. ( 90% completed) & 52nd above floor work in progress.
15) External railing work 95% completed till 39th floor , 40th to 51st work 90% completed & 52nd and above floor work in progress.
16) Podium level internal painting in progress.
17) Podium P1 To P7 area flooring screed work in progress. ( 70% completed )
18) Internal road for customers from Fit-out possession is completed.
19) Tower A both staircase finishing is in progress.
20) Typical lobby light fitting installation completed .
21) UG level triple height main entrance lobby work started.
22) Project water supply line work completed 100% & building water distribution system commissioned.
23) possession handover of 100+ flats
24) UG level triple height main entrance lobby & p8 level amenity area is operational
25) Project water supply line work completed & Building water distribution system commissioned
Pilatus
Tower raft -100% completed.
Basement – B1 complete, LG & UG complete,P1 to P7 slab casting done. STP installation work in progress .
Raft, Basements 1 to P8 level -100% RCC completed, 1st floor service area work completed, 10th to 32nd Slab completed. 33rd RCC Slab work in progress. Core area slab completed till 37th floor and 38th level slab in progress.
Finishing work 1) Block work completed till 28th floor & 29th floor work in progress. common area block work in progress.
2) Gypsum work completed till 28th floor & 29th and above floor work in progress
3) Water proofing completed from 9th to 13th floor & 14th to 19th floor work in progress.
Plumbing work in progress.
Firefighting lobby work in progress from 9th to 19th floor, flat area work from 9th to 19th in progress.
Electrical conducting work from 9th to 28th in progress.
Zermatt
Shore piling work
Excavation work started 
shore piling & capping beam work completed, soil retention work is in progress
Excavation work 90% completed.
Inclined rock anchoring 1st ,2nd & 3rd level work completed.
PCC started for podium areas & tower footprint area 100% completed)
Tower raft reinforcement work commenced & casting work started